Buc-ee's Ocala Update: Site Plan Passes Engineering Review as I-75 Exit at NW 49th Street Takes Shape

Crews drive bridge foundation piles for the new I-75 interchange at NW 49th Street. AI-generated illustration of pile-driving work; not a photo of the site.

Business
2026-09-295 min read

Buc-ee's Ocala Update: Site Plan Passes Engineering Review as I-75 Exit at NW 49th Street Takes Shape

This is a business news article published on 2026-09-29 covering local Marion County, Florida news. The Buc-ee's Ocala site plan passed the county engineer's review in June 2026 and FDOT says its contractor is in the pile-driving phase for the new NW 49th Street exit, but no opening date has been set.

Updated 2 days ago
O
Only In Ocala Editorial TeamLocal Content Specialists ยท 8+ years in Marion County
Share:
Buc-ee's has zoning approval and a site plan moving through county review for a travel center in Ocala, but no opening date. In June 2026 the major site plan passed the Marion County engineer's review, and in November the company asked the county for one more addition: an 82-by-14-foot mural facing Interstate 75. Buc-ee's own locations page lists two Florida stores, Daytona Beach and St. Augustine, and does not list Ocala.

The store is waiting on a new I-75 exit at NW 49th Street, which the Florida Department of Transportation is building now. FDOT's project page puts completion in fall 2028. A project flyer FDOT posted in August 2026 gave summer 2028 and described the current phase: crews driving large piles east and west of I-75 and in the median to serve as the "legs" of the interchange's two bridges.

Correction, Nov. 26, 2026: An earlier version of this story reported a 2029 opening target that did not come from Buc-ee's or a public record. Buc-ee's has not published an opening date. This story now relies only on Marion County, FDOT and Buc-ee's records.

Update, Nov. 25, 2026: Buc-ee's has asked the county to amend its zoning approval to add an 82-by-14-foot mural to the site's generator enclosure wall, facing I-75; the Planning and Zoning Commission hears the request on Nov. 30. Details are in our story on the Buc-ee's mural request.

Update, Oct. 3, 2026: The land on the other side of the new exit has a plan too. A 105-acre mixed-use project called NW 49th Street Gateway, with up to 535 homes, a 500-room hotel and 450,000 square feet of retail at NW 44th Avenue and NW 49th Street, won a recommendation of approval from the county Planning and Zoning Commission on Sept. 28, and the County Commission approved it 5-0 on Oct. 20. Details are in our story on the NW 49th Street Gateway plan.

Where Is the Ocala Buc-ee's Going?



County records put the travel center at 3790 NW 35th Street Road, east of I-75 and about 1.75 miles south of W Highway 326. The land was carved from a 464-acre tract owned by Baldwin Angus Ranch. The zoning limits commercial use to about 32.83 acres, with the final boundary to be set once FDOT and the county settle the I-75 and NW 35th Street Road rights-of-way; the county's 2026 records list the parcel at 34.61 acres. When county planners described the site in November 2026 it was still undeveloped. NW 35th Street Road had been built to the southern tip of the property, where it stops for now and will later connect to the new interchange.

Marion County commissioners approved the rezoning 5-0 on February 21, 2023, turning general agricultural land into a planned unit development the county's records call the Ocala Travel Center. The case was handled by Marion County, not the City of Ocala.

What Will the Travel Center Include?



The 2023 master plan approved with the rezoning and the 2026 major site plan filed with the county describe a large-format travel center:

FeaturePlanned
Building74,000 sq ft on the 2026 site plan (80,000 sq ft on the 2023 master plan)
Fueling positions120 (three canopies on the 2023 master plan)
Electric vehicles23 EV spaces on the 2026 site plan (28 on the 2023 master plan)
Car parking777 standard spaces plus 21 accessible on the 2026 site plan (750 standard on the 2023 master plan)
RV / bus parking11 spaces
Diesel exhaust fluid (DEF)8 positions
Pole signUp to 125 feet tall
Other structures50 feet maximum height


The building on the 2026 site plan is 74,000 square feet, smaller than the 80,000 square feet in the 2023 master plan; Buc-ee's has not announced a final figure. The county's 2023 staff report is explicit on one point that surprises many drivers: this is not a truck stop, and trucks are not allowed. The tall sign came with a condition as well. During site plan review, Buc-ee's had to provide a line-of-sight analysis or other documentation showing that 125 feet is the minimum height needed for visibility.

How Far Along Is the Store?



County records trace slow, steady progress. In September 2025, Kimley-Horn, the engineering firm working for Buc-ee's, asked the county's Development Review Committee to waive the rule that site surveys be less than 12 months old, saying nothing on the land had changed since the last survey.

Two utility agreements were on the County Commission's April 21, 2026 agenda. The first, with Baldwin Angus Ranch, covers a public sewer lift station sized to serve both the Buc-ee's and future development on the ranch. The second has the county pay about $50,000 for FDOT to lay a sewer casing under the new road during interchange construction, with Buc-ee's reimbursing the county. County utilities staff wrote that installing it now costs far less than drilling under a finished road later.

On June 2, 2026, the major site plan cleared the county engineer's review on its third round, after the first two drew requests for changes, and it went on the Development Review Committee's June 8 agenda. The November mural request is the latest step.

The I-75 at NW 49th Street Interchange



The new exit is north of Ocala, south of SR 326. According to FDOT's project page (Financial Project ID 435209-1, last updated September 22, 2026):

- Design: a diverging diamond interchange (DDI), which moves traffic to the left side of the road between two signals so drivers can turn left without crossing oncoming traffic. It includes pedestrian and bicycle accommodations and lighting.
- Cost and contractor: $59.4 million for construction, built by Lane Construction Corp.
- Schedule: construction began in spring 2026, and FDOT estimates completion in fall 2028.
- Purpose: FDOT says the exit will handle future traffic growth in northern Marion County, relieve the surrounding interchanges and provide access to the planned Buc-ee's.



FDOT aerial design plan of the I-75 at NW 49th Street diverging diamond interchange in Ocala, showing the new bridge and the Marion County NW 49th Street and NW 35th Street extensions
FDOT's design for the I-75 at NW 49th Street interchange. The Marion County NW 35th Street extension curves south from the east side of the interchange. Image: Florida Department of Transportation (FPID 435209-1).




Marion County is paying part of the bill. Under a locally funded agreement with FDOT signed in July 2024, the county agreed to contribute $8,419,860 toward the interchange. A second agreement, on the County Commission's Nov. 18, 2025 agenda, would let FDOT build on county right-of-way to tie the interchange into NW 35th Street, NW 44th Avenue and NW 49th Street, and would have the county take over those pieces on completion and maintain the community aesthetic feature: an "Ocala" welcome sign on the bridge over southbound I-75 that, in FDOT's words, pays homage to the area's equine history.

The exit is part of FDOT's Moving I-75 Forward initiative, two related projects covering 33 miles from SR 44 in Wildwood to SR 326 in Ocala that add auxiliary lanes in both directions and replace and widen bridges. FDOT District 5 posts lane closures and construction updates on its project page.

What Is Still Unknown?



- An opening date. None has been published, and Buc-ee's locations page does not list Ocala.
- The final store size. The 2026 site plan shows 74,000 square feet; the company has not confirmed a figure.

Only In Ocala will update this story as FDOT reaches new construction milestones and as the county and Buc-ee's release more details. For more on getting around the area, see our guides to EV charging in Ocala, driving from Ocala to Orlando and Ocala to Gainesville, and our overview of Marion County.

Sources, checked Nov. 26, 2026: Marion County staff report, case 230110ZP (2023 rezoning) and the County Commission's Feb. 21, 2023 vote record; Marion County staff report, case 261107ZP (Nov. 2026 mural amendment); Development Review Committee packet, Buc-ee's major site plan (June 2026); survey waiver request (Sept. 2025); developer's agreement and utilities system agreement (April 2026); FDOT locally funded agreement, FPN 435209-1-52-01; FDOT project 435209-1 and FDOT bridge construction flyer (Aug. 2026); Buc-ee's locations.

For drivers on this stretch of I-75 today, see our guide to hotels near I-75 in Ocala and our EV charging guide. Tesla has also applied to add Megacharger posts for electric semis at the Pilot by exit 358; details are in our Tesla Semi Megacharger story. The interchange's gateway feature is covered in our I-75 North Gateway story, and other openings around town are tracked on our new businesses in Ocala page.
Buc-ee's
I-75
NW 49th Street
FDOT
Interchange
Marion County