This is a government news article published on 2026-11-27 covering local Marion County, Florida news. Southwest of Ocala, the roads around the airport and West Port High School are being widened piece by piece. On Dec. 1, the county commission takes up land purchases and a state grant for SW 80th Avenue, and the city council votes on selling 2.84 acres of airport property for the SW 38th Street widening.

Updated Yesterday
By Only In Ocala Staff
Share:

On Ocala's southwest side, SW 80th Avenue and SW 38th Street are being rebuilt for more traffic, and the work is moving one parcel at a time: a stormwater pond site here, a corner lot there, a state grant for the next stretch. Several of those pieces land on two agendas on Tuesday, Dec. 1, 2026.



That morning, the Marion County Board of County Commissioners is asked to approve land purchases and a state grant for the SW 80th Avenue widening. That afternoon, the Ocala City Council votes on selling about 2.84 acres of Ocala International Airport property to the county for the SW 38th Street widening. Every item below comes from the two meeting agendas and the staff reports attached to them.



Close-up of a wooden survey stake with orange flagging tape in sandy soil at the edge of a two-lane asphalt road

AI-generated illustration. Not a photo of SW 80th Avenue or SW 38th Street.



SW 80th Avenue: from two lanes to four, in segments



The county is widening the 80th Avenue corridor in segments, and three of them appear on the Dec. 1 consent agenda.



Segment 2 runs about 1.9 miles from north of SW 34th Place to the State Road 40 intersection. The Florida Department of Transportation has offered the county a state grant of up to $1.3 million for its design and right-of-way phases. The grant agreement describes the job as a two- to four-lane widening, with signals, pedestrian facilities and drainage ponds. It says the design is already 60% complete. Design costs from before the agreement is signed do not count toward the reimbursement, and the county pays whatever the grant does not cover.



Segment 1B runs from SW 80th Street to about half a mile north of SW 38th Street. The county is asked to pay $821,462.37, plus closing costs, for about 5.4 acres at the northwest corner of SW 80th Avenue and SW 34th Place for a stormwater pond. Staff say the negotiated price avoids the added cost of condemnation.



Segment 3 covers about 3.3 miles of NW 80th/70th Avenue, from about 900 feet north of State Road 40 to about 600 feet south of U.S. 27. It is already under contract: commissioners hired Art Walker Construction in August. Two more purchase agreements, for $482,700 (about 1.5 acres) and $119,900 (a 0.69-acre parcel taken whole, with the county's contractor putting up replacement fencing), are on the agenda. A third item amends the construction contract so it qualifies for a state construction grant, which FDOT offered after the job had already been awarded.



The corridor is also drawing retail: we have reported on the approved Target site plan on SW 80th Avenue and the Shoppes off 80th near World Equestrian Center. Segment 3 was also one of the first road items the new commission saw, in our report on the Nov. 17 swearing-in.



SW 38th Street: airport land for a wider road and a roundabout



SW 38th Street crosses SW 80th Avenue and runs along the southern edge of Ocala International Airport. According to the city's staff report, the county is widening it between West Port High School and SW 60th Avenue and adding a roundabout at SW 67th Avenue Road.



To finish the job the county needs three pieces of airport land, about 2.84 acres in all:



  • a 2.58-acre stormwater pond site at the northeast corner of SW 38th Street and SW 80th Avenue;
  • 0.05 acres at the northwest corner of SW 38th Street and SW 67th Avenue Road;
  • 0.21 acres at the northeast corner of the same intersection.



The city bought that land in 1993 with state transportation money. Because of that, it could not sell without federal permission. The Federal Aviation Administration agreed: it issued a Letter of Release on Oct. 6, 2026, and a Deed of Release on Nov. 17, finding the land is no longer needed for the airport. Under the FAA's conditions, the city must put the $357,256.20 appraised value into an interest-bearing airport account, keep avigation rights over the land and keep it free of aircraft access and wildlife hazards. City staff recommend approval. The report says the road and roundabout will improve traffic to and from the south side of the airport, and the sale money will go to airport capital projects.



Also on the county's road list



  • Resurfacing on SW 38th Avenue, SW 3rd Street and SW 40th Avenue: Anderson Columbia Co. was the low bidder of four, at $835,667.13, to mill and resurface selected segments between SW 38th Court and State Road 40, restripe them and replace shoulder sod. It is paid for with the county's second local option fuel tax.
  • NE Highway 314 at E Highway 40: a $114,655 engineering task order for NV5 to design a third southbound lane on Highway 314, giving drivers separate left, through and right lanes where today the through and right-turn traffic share one. More right-of-way will be needed.
  • CR 42 at CR 25: an FDOT agreement reimbursing up to $256,368 of construction for safety changes recommended in a 2021 state study of CR 42 crashes. The plans include rebuilding the signal on a box span, better left-turn signal phasing, lighting, new pedestrian signals, crosswalks and more sidewalk.
  • NW/NE 49th and 35th streets: a $102,292 change order for engineering on the corridor that leads to the new I-75 interchange at NW 49th Street.



How to weigh in



The county items are on the consent agenda, which passes in a single vote unless a commissioner pulls an item for discussion. The board meets at 9 a.m. in the McPherson Governmental Campus Auditorium, 601 SE 25th Ave. The airport land sale is item 10h under general business at the City Council's 4 p.m. meeting in council chambers on the second floor of City Hall, 110 SE Watula Ave. Both meetings are open to the public. The rest of the month's meetings are in our December public meetings guide, and this week's state lane closures are in Ocala road work for Nov. 29-Dec. 5.



Sources: Marion County Board of County Commissioners agenda for Dec. 1, 2026 (consent items 7.4.1, 7.4.2, 7.4.7, 7.4.10, 7.6.2, 7.6.3, 7.6.5, 7.6.6 and 7.6.7), with the staff reports, the FDOT State Funded Grant Agreement for SW 80th Avenue Segment 2 and the draft resurfacing contract; Ocala City Council agenda for Dec. 1, 2026 (item 10h), with the staff report, FAA cover letter and release documents. All on the county's and city's Legistar sites, read Nov. 27, 2026. No construction dates appear in these documents. AI tools helped gather the sources and draft this page; each fact was checked against those sources before publishing.

SW 80th Avenue
NW 80th Avenue
SW 38th Street
road widening
Ocala International Airport
FDOT
Marion County Commission
Ocala City Council
roundabout
CR 42
Highway 314
Ocala
Marion County

Related Ocala Guides

More context and planning resources from Only In Ocala.

Related Content

Discover more of what Ocala has to offer